Watch these videos when you’d like to see a task done before you try it yourself. Each one uses an example line of poles and links to the page with the same steps in writing.

The first pole

This video shows you how to:
  1. Open Cable Tracing and click the first pole.
  2. Click the pole on its photo, and choose the framing under What is here?
  3. Click where the crossarm mounts on the pole, and then click each part the card names.
  4. Fill in the card: the type and length of the arm, its direction, the phases, the wire type and the status, and then the neutral.

The next pole and midspan

This video shows you how to:
  1. Answer the question on the next pole’s card, and choose its framing.
  2. Click each part, and confirm the direction and side.
  3. Click each wire where it crosses the yellow line at the midspan, and then click Next span.
  4. Add a guy wire and tie it to its anchor.
Written steps: Trace a line.

Find and fix issues

This video shows you how to:
  1. Read the Issues panel.
  2. Open the row for crossed wires and click Swap them.
  3. Open the midspan row and click Swap them.
  4. Dismiss a row by clicking Not an issue.
Written steps: Find and fix issues.

Export to DDS

This video shows you how to:
  1. Set a wire’s construction status.
  2. Open Export to DDS.
  3. Choose the construction status, and type the design name and the utility name.
  4. Read the warnings.
  5. Export the DDSDI file.
Written steps: Export to DDS.

Export to SPIDAcalc

This video shows you how to:
  1. Open the SPIDAcalc export.
  2. Read the readiness list.
  3. Download the exchange file.
  4. If the list shows warnings, click a row to go to that pole.
Written steps: Export to SPIDAcalc.